Frequently Asked Question
Design Build Team
•
Question:
Can the Peer Reviewer be responsible for reviewing one element of the project (such as MPT) and complete design activities for a different element of the project (such as foundation design)?
•
Answer:
Generally it will not be permitted. The only exception would be if there are two peer review subconsultants on the design-build team. The second peer review would have to review design by peer reviewer #1.
Created by
Last Modified by
Julius B Sanders/PennDOT
on
11/06/2008
at
09:00:15 AM
Julius B Sanders/PennDOT
on
11/06/2008
at
11:21:23 AM